The general conditions of a contract should include all of the following EXCEPT:

Prepare for the Alabama Electrical Contractor Exam. Study with multiple choice questions, each with hints and explanations. Get ready for your certification!

The general conditions of a contract are designed to outline the fundamental aspects that govern the relationship between the parties involved, often focusing on administrative and legal elements of the contract rather than the specific technical elements of the work being performed.

The correct answer, which indicates that technical specifications should not be included in the general conditions, is based on the understanding that technical specifications are typically part of the contract documents that provide detailed requirements and standards for the work to be completed. These specifications detail the quality, materials, workmanship, and installation methods required for the project. Instead, the general conditions serve to address overarching issues such as the priority of the documents, procedures for change orders, and financial matters like retainage.

In contrast, the priority of the documents is critical because it establishes which documents will take precedence in case of conflicting information. The inclusion of change orders is essential as it outlines how modifications to the original contract will be handled, ensuring that there is a clear process for both parties to follow. Retainage information is also important as it addresses how much money will be withheld until the project is satisfactorily completed, protecting the interests of the project owner. Thus, while all other options are integral to the general conditions of a contract, technical specifications belong to a different category

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy